Hi,

We are looking at running flush-joint 7 5/8" liner in 8 1/2" hole.

I am particularly interested in members' experience in the following:

1) How long was the casing/liner ?
2) What was the deviation and maximum dog-leg severity ?
3) How competent was the hole,and was it gauge or washed out ?
4) Did the casing/ liner go to bottom easily ?
5) Were centralisers run and what type ?
6) What mud was it run in ?
7) Was it rotated ?
8 ) How was ECD managed ?
9) Was cement bond checked, and what was found ?
10) How many times has this been done that you know of ?

I'd appreciate any input you have.

Thankyou

Nicky Riley
Drilling Engineer

Petrofac Energy Developments
To reply .. or to see the replies from others .. please login!
If you're not registered, please register... It's FREE
If you're too busy to do either, then mail to dave@relentlesspursuit.co.uk and we'll do it for you.
Hello! [ Login]